PSO 2008 Supply-Side Request for Proposals
PSO is currently seeking proposals for 450 to 600 megawatts of long-term supply-side generating capacity and associated energy available on June 1 of years 2012 through 2015.
Below is all the information currently available on the RFP. Check back frequently as additional information will be posted when available. Access to the Questions and Answers section of the RFP website can be obtained by sending the requestor’s (1) name, (2) company, (3) address, (4) phone number, and (5) e-mail address to PSO2008RFP@aep.com.
Anticipated RFP Schedule
- 07/10/2008 – Prequalification Submittal Due
- 07/14/2008 – Pre-bid Conference in Tulsa, OK
- 07/18/2008 - Prequalification Submittals Due*
- 07/30/2008 – Prequalification Results Announced*
- 08/22/2008 – Proposals Due
- 09/22/2008 – Short-list Identified
- 11/20/2008 – Selection of Award Group
*Note PSO's revision reflected on Q13.
Addendum No. 2 (issued July 18, 2008)
Addendum No. 2 has been issued to incorporate the changes in Prequalification Submittal and announcement dates as well as change to Article 19.3 – Changes of Environmental Law, of the PPA and TSA.
Pre-Bid Conference (held on July 14, 2008)
Addendum No. 1 (issued July 3, 2008)
Addendum No. 1 has been issued to address the recommendations of the Independent Evaluator in his Testimony filed on June 27, 2008.
Final RFP Documents (issued June 23, 2008)
Comments Received on Draft RFP (by June 9, 2008 Deadline)
PSO Response to Comments
Draft RFP Documents (issued May 14, 2008)